October 2020
Construction of the 3rd phase has now commenced. During the first phase, a large part of the access route was finished and outside work on most the houses is nearing completion.
August 2020
The facade of the houses in the first phase is now finished and at the same time the construction of the driveway commenced. The installation of the windows in the second phase has been completed.
July 2020
The sale of houses that are part of the second phase was launched in the middle of the month. Houses in the first phase are beginning to take on their final appearance.
June 2020
The houses in the 1st phase now have complete roof coverings and water pipes have been laid in the 1st to 3rd construction phase.
May 2020
The rough construction of the houses in the 2nd phase is now finished and at the same time infiltration pits for rainwater drainage were dug.
April 2020
At the beginning of the month, the ceilings of the second floors of the houses in the 1st phase were completed and the installation of windows commenced.
March 2020
Construction work is continuing on schedule. In the middle of March, the second floor was lined with bricks in the houses that are being built in the 1st phase.