December 2020
The model house that is part of the first phase of the project is almost finished. The access road to the G houses has newly been finalized and foundations were laid for the houses in the third phase.
October 2020
August 2020
The facade of the houses in the first phase is now finished and at the same time the construction of the driveway commenced. The installation of the windows in the second phase has been completed.
July 2020
June 2020
May 2020
April 2020
At the beginning of the month, the ceilings of the second floors of the houses in the 1st phase were completed and the installation of windows commenced.
March 2020
February 2020
Reinforced concrete ceilings were completed during the 1st phase of the project. The sewerage system was laid for all phases.
December 2019
Foundations have been completed in the houses that are being built in the 1st and 2nd phase.